Over 153,000 consumers across Sabah's east coast are getting electricity in three-hour shifts until Monday (30 Nov) after heavy rain washed away a transmission tower in Ranau.
From the original report
Sabah Electricity Sdn Bhd (SESB) aims to restore the 275-kilovolt (kV) transmission line to Sabah's east coast within six days, after a transmission tower collapsed in Ranau on Thursday (26 November).
SESB chairman Datuk Saadiah Aziz said full restoration of the supply and the grid is expected on 2 December, once the two affected transmission lines are reconnected.
…
This is a brief of a report by another newsroom. The excerpt below is from the original.
Read the full report at The Rakyat Post
The Rakyat Post
Read the full translated article in Japanese →
About this story
- Source
- The Rakyat Post
- Originally published
- Nov 27, 2026
- Updated here
- Nov 27, 2026
- Produced by
- Malaysia Times desk (brief) — reporting by the source
- Corrections
- Corrections log · Report an error