First LCS delivery pushed to April 2027 as five-ship project lags target
Photo: The Vibes
The five-vessel programme is 9.19 percentage points behind schedule and final handovers now extending to April 2029
From the original report
MALAYSIA'S first littoral combat ship (LCS), KD Maharaja Lela, is now scheduled for delivery in April 2027 after the contractor failed to meet its original December 2026 commitment, while construction of all five vessels remains behind target.
The Defence Ministry said overall progress on the RM11.227 billion project stood at 80.72% as at Sept 25, compared with the scheduled 89.91%.
…
This is a brief of a report by another newsroom. The excerpt below is from the original.
Read the full report at The Vibes
The Vibes
Read the full translated article in Japanese →
About this story
- Source
- The Vibes
- Originally published
- Oct 27, 2026
- Updated here
- Oct 27, 2026
- Produced by
- Malaysia Times desk (brief) — reporting by the source
- Corrections
- Corrections log · Report an error